Yorkshire Water invests £6.8m to replace 12km of water mains in Batley
11/16/2026
Yorkshire Water is investing £6.8m to replace 12km of water mains at Brownhill End, Batley Central and Batley Upper Low to provide a more reliable clean water supply and reduce bursts and leaks in the area.
The project will tackle hotspots in Batley and Birstall that have been prone to bursts and leaks in the past. Contract partners, United Infrastructure, start on Monday 23 November at Brownhill End, before moving to Upper Batley Low and Batley Central. The mains replacement stages are:
- £2.8m to replace over 5.4km of water main at Brownhill End
- £1m to upgrade over 2km of pipes at Batley Central
- £2.9m to replace 4.4km of clean water mains at Upper Batley Low
Replacing 12km of ageing pipes will help to reduce the likelihood of bursts and leaks in the future, improving the resilience of the local network and reducing the disruption caused by loss of supply.
Nichola Fairburn, project manager at Yorkshire Water, said: “We know bursts can cause significant disruption for our customers, which is why we’re investing £6.8m to upgrade 12km of water mains in Batley.
“The pipes in this area have needed a significant number of repairs over recent years, so replacing them now will help us reduce the risk of further bursts and provide a reliable clean water network for customers.
“We’ve been working closely with local highways and our partners United Infrastructure to keep disruption to a minimum and would like to thank residents and road users for their patience.”
The 12km of new mains in Batley is part of a £406m investment programme to replace over 1,000km of clean water pipes across the region to reduce leakage, bursts and supply disruptions.
Work will begin in Brownhill End on Monday 23 November, before getting underway in Upper Batley Low and Batley Central from Monday 30 November.
A number of temporary road closures and traffic management measures will be required while the work takes place. Yorkshire Water is holding a drop-in session at Batley Town Hall on Wednesday 25 November, where residents can meet the project team and find out more about the work planned in their area.
Work will pause over the Christmas break and is expected to complete by September 2027.