Replacing the clean water pipes in Kiveton Park and Wales

Mum bathing little girl
We’re spending £5.15million to replace over 6km of clean water pipes in Kiveton Park and Wales. These pipes are old and prone to bursting - replacing them now will reduce the risk of this happening in future; helping to save water and reduce disruption to you.

What we're doing

In May 2025 work began on a predicted 12-month programme to replace over 6km of clean water mains. This includes:

  • £2,818,750 investment to replace 3202m of clean water mains on Wales Road and Walesmoor Avenue, Kiveton Park
  • £2,062,275 investment to replace 2546m of clean water mains on Station Road
  • £259,953 investment to replace 378m of clean water mains on Mansfield Road

We’re working on:

  • the whole of Wales Road 
  • Station Road (between Church Lane and Hard Lane)
  • the whole of Walesmoor Avenue.

The sections we’re replacing are shown on the plan below in red:

Map highlighing the whole of Wales Road, Station Road (between Church Lane and Hard Lane) and the whole of Walesmoor Avenue.

 

Latest project updates

March 2026

The work is taking a little longer than planned but the team are progressing well and we’re hoping to have the whole project completed by November 2026.

The next stage of the work will be to replace the pipes that cross Kiveton Bridge. We’ve liaised with the local highways and as the road is narrow here, to complete the work safely, we’ll need to close the road while we complete this section. 

Station Road at Kiveton Bridge will be closed from 28 March until 12 April, while we complete this work. 

Pedestrian access will be maintained and our work won’t affect the train station. A signed diversion will be in place for all traffic, please plan ahead if you’re travelling in the area. 

Shuttle bus service

While our road closure is in place on Station Road there will be a free shuttle bus service operating to connect residents with the regular bus service at Swallownest. 

The timetable and route are shown below, this will be running from Saturday 28th March until Sunday 12th April and operated by Wilfreda Beehive.

Route:  Main Street, High Street (towards Swallownest via High Street, Rotherham Road, Main Street), Mansfield Road, Aston Way, Mansfield Road, School Road, Wales Road, Walesmoor Avenue (anti-clockwise), Wales Road (towards Swallownest direct via Wales Road).

All Travel South Yorkshire bus stops to be observed along the route.

Hail and Ride along Walesmoor Avenue.

Timetable

Daily

Swallownest, Main Street

05:30

Then at these times

00

30

until

23:30

23:57

 

 

 

 

 

 

 

Wales, Wales Road /Lestermoor Avenue

05:42

 

12

42

 

23:42

00:09

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Wales, Wales Road/Lestermoor Avenue

05:45

Then at these times

15

45

Until

19:45

20:15

20:43

21:13

21:43

22:13

22:43

23:13

22:43

Swallownest, Main Street

05:57

 

27

57

 

19:57

20:27

20:55

21:25

21:55

22:25

22:55

23:25

23:55

The plan below shows the normal bus diversion route in blue and the shuttle bus service in orange. 

 

August 2025

The team have installed over 1300m of new water main so far on the project.

During week commencing 25th August the team will move onto the next 100m section of work from Old Coach Road to just passed the first junction of Walesmoor Avenue, this section should take around 5 weeks to complete.

To keep everyone safe we’ll continue to use temporary traffic lights around our working area, these will be manually controlled between 7am and 7pm, 7 days a week.  We’ll also be closing the first junction of Walesmoor Avenue as we pass it, this will help to keep traffic flowing as we’ll not need to use an additional traffic light on here.

Vehicle access will be maintained for Walesmoor Avenue via Lestermoor Avenue and the second Walesmoor Avenue junction. 

July 2025

In May 2025 work began on Walesmoor Avenue and is progressing well; we’re hoping to have finished on here by 14th July.

Wales Road

From 14th July work will begin on the first 100m section of work on Wales Road, starting at the junction of Church Street and finishing just before Lodge Hill Drive. This section will take around 6 weeks to complete.

To keep everyone safe we’ll be using temporary traffic lights around our working area, these will move with our work as it progresses and will be manually controlled between 7am and 7pm, 7 days a week to help keep traffic flowing.

Want to know more?

If you’ve any questions, please contact the Customer Experience team on 0344 848 1099 quoting Capital YW.206170 (lines are open Monday to Friday 8am-5pm).

 

Will you need to interrupt my water supply as part of the work?

We may need to interrupt your supply for a short time while we complete this work, if we do, you’ll receive a hand delivered card notifying you of the dates and times in advance.

 

Priority Services

We want to make sure everyone is happy and safe, and we have lots of ways to help make that happen - you just need to let us know how we can help.

Register for Priority Services

 

Businesses

We understand these works are disruptive and we’d like to offer support where we can. If you would like information on claiming for loss of profit as a direct result of our works, please contact us on the number above and we’ll be happy to help.

More from us

Investing in Yorkshire

From fixing leaks to making new wetlands. From helping customers struggling with bills, to giving back by helping communities thrive.

Investing in Yorkshire

Friends at Ogden reservoir