Road reopens two weeks ahead of schedule

We've completed work to prevent sewer flooding to homes on West Street in Bailiff Bridge two weeks ahead of schedule.

Wakefield Road had been closed for seven weeks to ensure the safety of the local community and contract partners, Mott MacDonald Bentley.

Workers managed to complete the work ahead of schedule by using a technique to install the new sewer called auger boring, which is faster but not always possible due to ground conditions. Auger boring means two holes are dug and the new pipe is tunneled under the ground from one pit to the other. Due to the large amount of pipes and cables from other utilities under this section of Wakefield Road, the alternative would have been to hand-dig a trench which would have taken much longer. 

Some local homes previously suffered from flooding in times of heavy rainfall. Rain water from the road went into the sewer, overloading the system causing water to back up the pipes and flood homes and gardens. 

Jonathan LeMoine, Project Manager for Yorkshire Water said: “We appreciate that this scheme was disruptive to residents and road-users but we had no other option if our contractors were to work quickly and safely. 

“We’d like to thank anyone affected by the roadworks for their patience throughout this essential project.”

The project, costing £150,000, is part of a £3.8bn investment programme between 2015 and 2020. Our network of pipes stretches for 51,500 miles and collects, treats and returns to the environment 1 billion litres of water every day.

You might be interested in these articles

January 18, 2019
Ice house in city centre to showcase protecting homes from the freezing weather

An ice house has been assembled in Sheffield city centre by Yorkshire Water…

January 11, 2019
Update on Yorkshire Water’s £3 million scheme to lay six miles of new water pipes in Harrogate

The next phase of Yorkshire Water’s £3 million clean water pipe…

January 4, 2019
Work to lay a new water pipe in Otley Road, Harrogate

Yorkshire Water will start work on Monday 7th January on a scheme to lay a…

January 4, 2019
Yorkshire Water invests almost £8m in north Yorkshire treatment sites

Yorkshire Water is starting two schemes of investment worth £7.7m at two…

close
close
close